Our Achievement

Nagoya Port West 5th Pier Reinforcement

Work Summary

Project Name Nagoya Port West 5th Pier Reinforcement
Client Nagoya Port Terminal Public Corporation

Details

Steel Pipe Pile φ1,600mm t=19/16mm / L=70.5m 84 piles
φ1,600mm t=19/16mm / L=71.5m 126 piles
φ1,600mm t=22/19mm / L=70.5m 28 piles
φ1,600mm t=202/19mm / L=71.5m 42 piles
Total 280 piles

 