Kurushima Kaikyo Bridge 4A Cable Anchor Frame Work
                  
                
                  
                
                        
                    
                        
                    Construction Overview
- Project name
 - Kurushima Kaikyo Bridge 4A cable anchor frame construction
 - Client
 - Honshu-Shikoku Connecting Bridge Authority
 
Structure Specifications and Quantity
- First CAF
 - L=13.7m W=7.2m H=14.4m / Weight 282.2t 2 units
 - Second CAF
 - L=19.2m W=8.8m H=20.5m / Weight 681.5t 2 units