Mizushima LNG Base Construction with 6th Pier Renovation Work
Construction Overview
- Project name
- No. 6 pier modification work associated with the construction of Mizushima LNG terminal
- Client
- Taisei Construction Co., Ltd.
Structure Specifications and Quantity
- Jacket removal/transportation/installation
- W=245 t (Kudamatsu Port - Mizushima Port, Yamaguchi Prefecture)
- Steel pipe pile driving
- Straight pile / φ700mm t=11mm L=41.45m 4 pieces
25° diagonal pile / φ1,000mm t=15mm L=46.58m 6 pieces
25° diagonal pile / φ1,100mm t=17mm L=51.673m 6 pieces
- Reg grouting
- 23.6 m3 16 pieces
- Pca floor slab transportation/installation
- 0.7~30.0 t 25 pieces
- Pipe bridge removal/transportation/installation
- W=157 t (from Aioi Port, Hyogo Prefecture to Mizushima Port)