Construction Overview


Project name
Saigo Port (main port area) bow and stern mooring quay (-7.5m) seismic reinforcement quay construction

Orderer
Shimane Prefecture

Structure Specifications and Quantity


Steel pipe pile driving
φ1,200mm t=12mm / L=55.6~65.6m 24 pieces

Jacket installation
№1 Jacket 358 TF 1 unit
№2 Jacket 423 TF 1 unit