Taiwan Power Hsing-Ta Power Plant Offshore Unloading Pier and Link Bridge New Construction Project

森長組
森長組
森長組
森長組
森長組
森長組

Construction Overview


Project name
Taiwan Electric Power Co., Ltd. Xingda Power Station Outer Sea Wholesale Terminal and Connecting Pier New Construction Project

Orderer
Taiwan Power Company

Steel pipe pile driving work


Connecting pier
φ1,500mm L=46.0~55.0m / straight pile / 151 15.9° diagonal pile

Coal unloading pier
φ1,650mm L=65.0m / straight pile / 40 5.7° diagonal piles
φ1,200mm L=50.0m / 18 15.9° diagonal piles
φ1,200mm L=58.0~68.0m / Straight pile / 56 2.9° diagonal piles
φ1,500mm L=60.0~75.0m / Straight pile / 96 2.9°, 5.7°, 15.9° diagonal piles
φ1,100mm L=36~42m / 20 straight piles

Total
381 pieces


Other precast and steel girder installation